Project Status:
True North 400 committed funds to the project in October 2024. Bids were due to the city in Fall 2024, and a bid was awarded.
Construction began in February 2025 and True North 400 worked with the City of Alpharetta to hold a groundbreaking in March 2025.
Construction Updates:
- Clearing completed
- Initial erosion control has been installed
- Contractor is creating temporary access road for future construction of pedestrian bridges
What’s Next:
- Installing bridge foundation supports for bridge number two
- Construction of sewer line transfer platform to move wastewater between sewer lines