Encore Greenway Park and Gateway

Start Date

Spring 2022 (design); Fall 2024 (construction)

completion date

2025

total cid investment

$1,930,000

The future Encore Greenway Park will be located at North Point Parkway and Encore Parkway and create a gateway feature to connect to one of North Fulton’s most valuable amenities, the Big Creek Greenway. It will provide a critical connection from the Alpha Loop to the Big Creek Greenway. This project is a partnership between the City of Alpharetta and True North 400. It will benefit the North Point corridor by providing a more robust connection between two of the region’s premier trail systems so it can be better leveraged by those who live, work, and play in the North Point area and district beyond.

Encore Greenway Park Gateway Concept
Encore Greenway Park concept

Project Status:

True North 400 committed funds to the project in October 2024. Bids were due to the city in Fall 2024, and a bid was awarded.
Construction began in February 2025 and True North 400 worked with the City of Alpharetta to hold a groundbreaking in March 2025.

Construction Updates:

  • Clearing completed
  • Initial erosion control has been installed
  • Contractor is creating temporary access road for future construction of pedestrian bridges

What’s Next:

  • Installing bridge foundation supports for bridge number two
  • Construction of sewer line transfer platform to move wastewater between sewer lines

Groundbreaking Event

Financial commitment

$9,830,000

partners

  • City of Alpharetta