Project Status:
True North 400 committed funds to the project in October 2024. Bids were due to the city in Fall 2024, and a bid was awarded. Construction began in February 2025 and True North 400 worked with the City of Alpharetta to hold a groundbreaking in March 2025.
View the latest construction update flyer here.
Construction Updates:
Completed So Far:
- Installed helical piers for the boardwalk
- Constructed sewer line transfer platform to move wastewater between sewer lines
- Grading for retaining wall construction
- Storm drainage setup
- Site grading
Current Activity:
- Installing grass where construction activities are finalizing
- Installing handrails along the raised boardwalk underway
- Terraces on the plaza are being constructed
- Finishing the MSE walls
- Installing retaining wall with stone veneer
What’s Next:
- Placing beams and decking for bridges
- Finalizing electrical conduit work for future lighting