Old Milton Parkway at GA 400 Ramp

Start Date

February 2014

completion date

September 2014

total cid investment

$200,000

True North 400, in partnership with the Georgia Department of Transportation and the City of Alpharetta, completed the widening of the existing northbound GA 400 exit ramp at Old Milton Parkway. The improvement eliminated the shared left/right turn lane in favor of a true dual left and dual right movement. The entire project was constructed within the existing right-of-way.

Old Milton Parkway Ramp Before
Before

Financial commitment

$450,000