Windward Parkway Phase II – Triple Left Turn Lane

Start Date

completion date

Fall 2020

total cid investment

True North 400’s contribution totals just over $1 million, which includes all design and construction management.

This project was designed to reduce congestion at the high-traffic Georgia 400 interchange at Windward Parkway by adding a triple-left-turn lane that extends along westbound Windward Parkway to Deerfield Parkway and Westside Parkway. The project was a part of an ongoing effort to improve transportation flow for drivers along and entering Windward Parkway from Georgia 400 northbound.

The Windward Parkway triple-left project was envisioned in the CID’s Blueprint North Fulton master plan and is also included in the second iteration of the plan, Blueprint North Fulton 2.0.

Windward Parkway Phase 2 Triple Left Turn Added
After
Windward Parkway Before Triple Left Turn Added
Before

Financial commitment

This project cost an estimated $7.18 million.